Broadway Road Sewer Main Replacement Project

The following also is provided in Spanish. Lo siguiente también es provisto en Español.

Segment 2C

Installation of the 30" sewer main is taking place between 12th and 16th Streets. Construction of manholes is occuring between 7th and 12th Streets and 12th to 16th Streets.

8th Street will have no access to or from Broadway Road between May 15 and June 15 (dates are approximate and subject to change).

Segment 2B

Complete

Segment 2A

Complete